Sunday, February 18, 2018

PMP Training - Key Reference Notes


Key notes for use in review the day prior to test day

Integration

·        Integrated Change ControlEvaluate (always first), Identify Options, Approval (internal, customer)       

Scope

·        Scope Baseline – Project scope statement, WBS, WBS Dictionary

Time (Schedule)

·        Schedule Baseline – Start and stop dates for each activity
·        Float (Slack) – LS – ES or LF – EF
·        Crash: increases cost, shortens time by increasing resources on an activity, law of diminishing returns
·        Fast-Track: increases risk, shortens time by performing critical path activities simultaneously (0 float); often requires rework
·        Critical Chain Method – includes buffers in-between activities
·        Always advise of impact of change first
·        Know how to draw a network diagram and determine length of critical path
·        Estimate Types (for cost and time)
o   Analogous – top down (faster, less accurate)
o   Bottom Up – (takes longer, more accurate)
o   Parametric – relationship between two variables (units per hour)
o   3 Point/PERT – Optimistic, Pessimistic, Most Likely (gives risk assessment)
§  Weighted/Beta: (P + 4M + O) / 6
§  Simple/Triangular: (P + M + O) / 3
§  Standard Deviation/Range: (P-O) / 6; EAD + SD
o   Heuristics – Rule of thumb (ex: design is always 15% of time)

Cost

·        Cost Baseline – Time-phased cost budget (funds the project manager has to manage; incl. contingency reserves)
·        Earned Value Calculations (understand and practice, but no need to memorize formulas)
o   Earned Value (EV) = Actual % Complete * Budget at Completion (BAC)
o   Planned Value (PV) = Planned % Complete * Budget at Completion (BAC)
o   Actual Cost (AC) = Amount spent so far
o   Cost Variance (CV) = EV – AC (+ is good)
o   Schedule Variance (SV) = EV – PV (+ is good)
o   Cost Performance Index (CPI) = EV / AC (>1 is good)
o   Schedule Performance Index (SPI) = EV / PV (>1 is good)
o   Estimate at Completion (EAC) = BAC/CPI (standard; varies if rate is expected to change)
o   Estimate to Completion (ETC) = EAC – AC
o   Variance at Completion (VAC) = BAC – EAC
o   To-Complete Performance Index (TCPI) = (BAC-EV) / (BAC-AC)     
·        Value Analysis – how can decrease cost while maintaining scope
·        Reserves (includes cost and time)
o   Contingency – known unknowns; calculated
o   Management – unknown unknowns, lump sum
·        Accuracy of Estimates
o   Rough Order of Magnitude – (initiating) -25% to +75%
o   Budget – (planning) -10% to +25%
o   Definitive – (as progresses) +/- 10%

Quality

·        Quality is about meeting requirements
·        Prevention over Inspection
·        Quality Assurance (Executing Process) – evaluate methods/“overall”
·        Quality Control (Monitoring & Controlling Process) – evaluate deliverables
·        Quality Audit (Executing) – evaluate compliance and effectiveness
·        Process Analysis (Executing) – evaluate how to improve process
·        Quality Diagramming Methods (7 Basic Tools) *know which is used when
o   Cause and Effect Diagram (Fishbone, Ishikawa) – root cause analysis 
o   Flow Chart – process map
o   Checksheet – count of issues during inspection
o   Pareto Diagram – issues by frequency (high to low); where to focus efforts
o   Histogram – Same as Pareto but not in order
o   Control Chart – specification limits, control limits, where data points are
o   Scatter Diagram – two variables to detect if there is correlation
·        Design of Experiments (DOE) – determine which variables improve quality (fast, accurate)
·        Gold plating – should be avoided. Rarely what customer wants; focus on delivering requirements

Human Resources (People/Teams)

·        Sources of Conflict (in order of frequency) – Schedule, priorities, resources, technical opinions, procedures, cost, personalities
·        Motivation Models
o   Tucker Model – Forming, Storming, Norming, Performing, Adjourning
o   McGregor’s Theory
§  X – people avoid work, watch them
§  Y – people want to achieve, direct themselves
o   Maslow’s Hierarchy – (in order of need) Psychological, safety, social, esteem, self-actualization
o   Herzberg’s Theory – basic working conditions are required but not a motivator; what motivates people is responsibility, growth, recognition, and self-actualization

Communications

·        Communication Channels – [N (N – 1)]/2 *know this formula

Risk

·        Risk Audit (Monitoring & Controlling Process) – evaluate process and effectiveness of responses
·        Information-Gathering Techniques
o   Brainstorming – collaborative/building upon each other’s ideas
o   Delphi – achieve consensus among experts
o   Interviewing – ask stakeholders
o   Root Cause Analysis
·        Qualitative – levels of probability; impact
·        Quantitative – #s
·        Determining Quantitative Probability and Impact
o   Any info gathering technique +
o   Sensitivity Analysis – compare potential impacts (ex: tornado diagram)
o   Expected Monetary Value (EMV) = Probability * Impact
o   Monte Carlo – simulation to determine likelihood of particular cost and schedule outcomes
·        Responses Threat (Opportunity)
o   Avoid (Exploit) – eliminate cause
o   Mitigate (Enhance) – reduce probability, lessen risk
o   Transfer (Share) – deflect, allocate
o   Accept – do nothing (active acceptance – create contingency plan)
·        Workaround – how to respond when risk occurs that had no response planned

Procurement

·        Procurement Audit (Closing Process) – evaluate how can improve in future
·        Contract Types *Known when to use which type
o   Fixed Price (FP) – Risk on seller, well-defined specifications, less management required
o   Time and Material (T&M) – Risk on buyer, uncertain scope, quick start, management required
o   Cost Reimbursement (CR) – Risk on buyer, expertise utilized, audits required
·        Items to Negotiate (in order) – Scope, Schedule, Price
·        Procurement manager is only one who can change contract


No comments:

Post a Comment